Overall Rating | Silver - expired |
---|---|
Overall Score | 62.73 |
Liaison | Tina Woolston |
Submission Date | Aug. 1, 2011 |
Executive Letter | Download |
Tufts University
OP-23: Stormwater Management
Status | Score | Responsible Party |
---|---|---|
1.00 / 2.00 |
John
Vik Grounds Supervisor Facilities |
"---"
indicates that no data was submitted for this field
None
Does the institution have a policy, plan, and/or strategies to reduce stormwater runoff from new development projects? :
No
None
Does the institution have a policy, plan, and/or strategies to reduce stormwater runoff from ongoing campus operations? :
Yes
None
A brief description of the institution's stormwater management initiatives:
Tufts follows Massachusetts' stormwater policies and regulations. See http://www.mass.gov/dep/water/wastewater/stormwat.htm for details.
Sophia Gordon Hall has a stormwater management system that exceeds the requirements of the Massachusetts Department of Environmental Protection Stormwater Management Policy and includes a reduction in peak stormwater runoff. The total site area of Sophia Gordon Hall is 50,000 square feet. 58% of the site (approximately 21,000 square feet) is pervious (i.e. water can penetrate directly into the soil). A number of catch basins, a Stormtech infiltration system and an underground detention Advanced Drainage System (ADS) reduce the rate of runoff into the city's storm sewer by maintaining or holding the water and releasing it slowly.
None
The website URL where information about the institution's stormwater management initiatives, plan or policy is available:
---
None
Does the institution have a living or vegetated roof?:
Yes
None
A brief description of the institution's living or vegetated roof:
The Tisch library has a vegetated roof. For more information, see: http://tuftsjournal.tufts.edu/2010/06_1/briefs/02/
None
Does the institution have porous paving?:
No
None
A brief description of the institution's porous paving:
---
None
Does the institution have retention ponds?:
No
None
A brief description of the institution's retention ponds:
---
None
Does the institution have stone swales?:
No
None
A brief description of the institution's stone swales:
---
None
Does the institution have vegetated swales?:
No
None
A brief description of the institution's vegetated swales:
---
None
Does the institution employ any other technologies or strategies for stormwater management?:
Yes
None
A brief description of other technologies or strategies for stormwater management employed:
Sophia Gordon Hall
Erosion and sediment from building sites can have considerable ecological consequences. During construction, a comprehensive erosion and sedimentation (E&S) control plan required the project to keep sediment from entering nearby storm sewers by installing temporary silt fencing, placing silt fabric over catch basins, and sweeping the street carefully.
The Athletics project (Steve Tisch Sports and Fitness Center) includes below-grade “Stormtech” storage chambers which retain stormwater runoff from the adjacent paved areas (primarily the parking lot behind the Eliot-Pearson School, and driveway along Gantcher Field House), allowing some infiltration and some temporary retention so that post-construction peak discharge rates from the overall site do not exceed pre-construction peak discharge rates from the overall site.
Data source(s) and notes about the submission:
---
The information presented here is self-reported. While AASHE staff review portions of all STARS reports and institutions are welcome to seek additional forms of review, the data in STARS reports are not verified by AASHE. If you believe any of this information is erroneous or inconsistent with credit criteria, please review the process for inquiring about the information reported by an institution or simply email your inquiry to stars@aashe.org.