OP-19: Construction and Demolition Waste Diversion
Status | Score | Responsible Party |
---|---|---|
0.92 / 1.00 |
Dave
Merchan Project Engineer University Facilities |
"---"
indicates that no data was submitted for this field
None
Amount of construction and demolition materials recycled, donated, or otherwise recovered :
683
Tons
None
Amount of construction and demolition materials landfilled or incinerated :
57.90
Tons
None
A brief description of programs, policies, infrastructure investments, outreach efforts, and/or other factors that contribute to the diversion rate for construction and demolition waste:
We don't have a formal policy in place but we attempt LEED Materials and Resources credit 2 on every new LEED construction project. All of our construction debris is handled by a single source contractor, through the construction administrator (aka general contractor) on larger jobs. On smaller jobs, we do not have any policies in place.
Data source(s) and notes about the submission:
---
The information presented here is self-reported. While AASHE staff review portions of all STARS reports and institutions are welcome to seek additional forms of review, the data in STARS reports are not verified by AASHE. If you believe any of this information is erroneous or inconsistent with credit criteria, please review the process for inquiring about the information reported by an institution or simply email your inquiry to stars@aashe.org.